In the precedence diagramming method, which of the following is a logical relationship for the activities?

In the precedence diagramming method, which of the following is a logical relationship for the activities?

PrepAway - Latest Free Exam Questions & Answers

A.
Finish-to-start

B.
Applying leads and lags

C.
Activity-on-node

D.
Dependency determination