During the initial stages of the project, what do activity attributes include?

During the initial stages of the project, what do activity attributes include?

PrepAway - Latest Free Exam Questions & Answers

A.
Activity name, dependencies, assumptions

B.
Activity ID, WBS ID, activity name

C.
Activity ID, assumptions, constraints

D.
Activity name, WBS ID, activity description

One Comment on “During the initial stages of the project, what do activity attributes include?

  1. Alexander says:

    Correct.
    6.2.3.2 Activity Attributes
    “During the initial stages of the project, they include the activity identifier (ID), WBS ID,
    and activity label or name, and when completed, may include activity codes, activity description, predecessor activities, successor activities, logical relationships, leads and lags (Section 6.3.2.3), resource requirements, imposed dates, constraints, and assumptions.”