What is the lowest level in the WBS at which the cost and activity durations for the work can be reliably esti

What is the lowest level in the WBS at which the cost and activity durations for the work can be reliably estimated and managed?

PrepAway - Latest Free Exam Questions & Answers

A.
Work product

B.
Work package

C.
Project deliverable

D.
Scope baseline