PrepAway - Latest Free Exam Questions & Answers

If the PMO receives the following information, which project should they be the MOST concerned about?

The project management office is worried about the quality of the company’s various projects. They want to know which projects are having problems and which ones are doing well. If the PMO receives the following information, which project should they be the MOST concerned about?

PrepAway - Latest Free Exam Questions & Answers

A.
Project A with a benefit cost ratio of 2.3

B.
Project B with a benefit cost ratio of 1.3

C.
Project C with a benefit cost ratio of negative 2.3

D.
Project D with a benefit cost ratio of negative 1.3

2 Comments on “If the PMO receives the following information, which project should they be the MOST concerned about?

  1. Alexander says:

    Negative cost-benefit ratio can’t be greater than 1 If the number is less than 1.0, then the cost-benefit analysis is negative. If it’s greater than 1.0, then there’s a positive return.




    0



    0

Leave a Reply