What is the expected activity cost for a project having a most likely cost of $140, a best case scenario of $1

What is the expected activity cost for a project having a most likely cost of $140, a best case scenario of $115, and a worst case scenario of $165?

PrepAway - Latest Free Exam Questions & Answers

A.
$115

B.
$138

C.
$140

D.
$165