Parametric Estimating is done as a part of which process:
A.
Estimate Activity Durations
B.
Sequence Activities
C.
Develop Schedule
D.
Estimate Activity Resources
Explanation:
Tools and Techniques for Estimate Activity Durations are: Analogous estimates , Parametric Estimating, Three-Point Estimates and Reserve Analysis.