What is the status of a project if the Cost Performance Index is 1.25 and the Schedule Performance Index is 0.

What is the status of a project if the Cost Performance Index is 1.25 and the Schedule Performance Index is 0.75?

PrepAway - Latest Free Exam Questions & Answers

A.
Under budget and behind schedule

B.
Over budget and ahead of schedule

C.
Under budget and ahead of schedule

D.
Over budget and behind schedule