Which of the following must not performed in the project initiation process?

Which of the following must not performed in the project initiation process?

PrepAway - Latest Free Exam Questions & Answers

A.
Evaluate historical information

B.
List down business need

C.
List down stakeholders

D.
Create scope statement

Explanation:
Scope statement generally created in planning phase.
All others are done in initiation phase.