What is the actual status of this project?

The project manager calculated a schedule performance index of 0.8 and a cost performance index of 1.1 for the project. What is the actual status of this project?

PrepAway - Latest Free Exam Questions & Answers

A.
Behind schedule and over budget

B.
Behind schedule and under budget

C.
Ahead of schedule and under budget

D.
Ahead of schedule and over budget