Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

PrepAway - Latest Free Exam Questions & Answers

A.
Cost baseline

B.
Cost forecasting

C.
Cost variance

D.
Cost budgeting