A project manager has just been assigned to a new project and has been given the approved project charter. The FIRST thing the project manager must do is:
A.
Create a project scope statement.
B.
Confirm that all the stakeholders have had input to the scope.
C.
Analyze project risk.
D.
Begin work on a project management plan.