PrepAway - Latest Free Exam Questions & Answers

Which of the following schedule network analysis techniques is applied when a critical path method calculation

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

PrepAway - Latest Free Exam Questions & Answers

A.
Applying calendars

B.
Resource Leveling

C.
Resource Planning

D.
Resource Conflict Management


Leave a Reply