A project manager is asked to select a contract type for a new software development project that has complete, detailed requirements. Which is the BEST contract to choose?

PrepAway - Latest Free Exam Questions & Answers

A.
Cost reimbursable (CR)

B.
Fixed price (FP)

C.
Time and material (T&M)

D.
Cost plus fixed fee (CPFF)


Leave a Reply