Who is responsible for issuing the project charter?

Who is responsible for issuing the project charter?

PrepAway - Latest Free Exam Questions & Answers

A.
The project sponsor

B.
The senior Project Manager

C.
The project team

D.
The project manager

Explanation:
The project sponsor creates and issues the project charter.