Resource reallocation from non critical to critical activities is an example of which Project Scheduling technique:
A.
Critical Path Method
B.
Schedule Compression
C.
Resource Leveling
D.
What if Analysis
Explanation:
Resource Leveling: Allocate scare resources to critical path activities first.