What tool or technique of Estimate Activity Durations uses parameters such as duration, budget, size, weight, and complexity from a previous, similar project as the basis for estimating the same parameter or measure for a future project?

PrepAway - Latest Free Exam Questions & Answers

A.
Bottom-up estimating

B.
Analogous estimating

C.
Parametric estimating

D.
Three-point estimates