Which one of the following is true regarding the change control board?

Which one of the following is true regarding the change control board?

PrepAway - Latest Free Exam Questions & Answers

A.
Describes how changes are managed.

B.
Approves or rejects change requests.

C.
Needs updated project management plans to approve or reject a change.

D.
Describes how changes are documented.