Which of the following MUST NOT performed in project initiation process?

Which of the following MUST NOT performed in project initiation process?

PrepAway - Latest Free Exam Questions & Answers

A.
identify the requirements.

B.
identify business need.

C.
create project scope statement.

D.
create project charter.

Explanation:
project scope statement created during project planning phase.