With which of the following would it be BEST for the project manager to ask the attorney for help?

A company attorney, newly hired by the company, walks into the project manager’s office and tells her that he is ready to work with her on the procurement process. The project manager has little experience with procurement, so she is excited to have the assistance. With which of the following would it be BEST for the project manager to ask the attorney for help?

PrepAway - Latest Free Exam Questions & Answers

A.
Claims administration, audit results, and updating organizational process assets

B.
Contract change control system, payments, and change requests

C.
Recommended corrective actions, performance reporting, and records management system

D.
Procurement documentation, project management plan updates, and procurement management plan updates