Which of the following would be the MOST appropriate thing to do during the monitoring and controlling process group?

A.
Implement recognition and reward systems.
B.
Obtain sign-off of the product of the project.
C.
Issue performance reports.
D.
Keep everyone focused on completing the project to the charter.