Which of the following is not true for a Responsibility Assignment Matrix (RAM):

A.
Defines what project member is responsible for each activity
B.
Defines responsibilities for each WBS component
C.
Defines all people associated with each activity
D.
Text description of roles, responsibilities, authorities
Explanation:
The Responsibility Assignment Matrix (RAM) details the different tasks for the people listed in the matrix chart.