PrepAway - Latest Free Exam Questions & Answers

Which of the following is CORRECT?

Which of the following is CORRECT?

PrepAway - Latest Free Exam Questions & Answers

A.
The critical path helps prove how long the project will take.

B.
There can be only one critical path.

C.
The network diagram will change every time the end date changes.

D.
A project can never have negative float.


Leave a Reply