A project manager is asked to select a contract type for a new software development project that has complete, detailed requirements. Which is the BEST contract to choose?

A.
Cost reimbursable (CR)
B.
Fixed price (FP)
C.
Time and material (T&M)
D.
Cost plus fixed fee (CPFF)