Which is an input to the Collect Requirements process?

Which is an input to the Collect Requirements process?

PrepAway - Latest Free Exam Questions & Answers

A.
Requirement documentation

B.
Organizational process assets

C.
Requirements management plan

D.
Stakeholder register

One Comment on “Which is an input to the Collect Requirements process?

  1. Ahmet Can Aykut says:

    Answer is wrong.Please refer to 5.2 of PMBOK v5

    1 Scope management plan
    .2 Requirements
    management plan
    .3 Stakeholder management
    plan
    .4 Project charter
    .5 Stakeholder register