When working in a matrix environment, all of the following are true regarding the Manage Project Team process

When working in a matrix environment, all of the following are true regarding the Manage Project Team process except for which one?

PrepAway - Latest Free Exam Questions & Answers

A.
Communication methods and issue logs are used to create performance appraisals, provide feedback, and track issues.

B.
Managing project teams in a matrix environment is often a critical success factor for the project.

C.
Loyalty issues might arise when managing projects in a matrix environment.

D.
It’s the project manager’s responsibility to make certain this dual reporting relationship is managed effectively.

Explanation:
Communication methods are not a tool and technique of the Manage Project Team process.