When working in a matrix environment, all of the following are true regarding the Manage Project Team process except for which one?

A.
Communication methods and issue logs are used to create performance appraisals, provide feedback, and track issues.
B.
Managing project teams in a matrix environment is often a critical success factor for the project.
C.
Loyalty issues might arise when managing projects in a matrix environment.
D.
It’s the project manager’s responsibility to make certain this dual reporting relationship is managed effectively.
Explanation:
Communication methods are not a tool and technique of the Manage Project Team process.