You are a project manager of ABC organization. You are estimating the project in initiation phase.
What level of accuracy you can expect?

PrepAway - Latest Free Exam Questions & Answers

A.
-75 percent to +75 percent

B.
-25 percent to +25 percent

C.
-50 percent to +50 percent

D.
-50 percent to +100 percent

Explanation:
In the project initiation phase estimation is rough therefore it can fluctuate -50 percent to +100 percent.