Draw the precedence diagram for the dependencies and activity times below to answer the question. Use AON or another technique to derive the answer using F-S relationships.
What is the critical path duration for the given schedule network?

A.
22
B.
23
C.
24
D.
25
Bad bad Q!
Where is the schedule network dude?
0
0