The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected:
Actual cost = $50,000
Plan cost = $45,000
Earned value = $40,000
What is the cost performance index?

A.
0.80
B.
0.89
C.
1.13
D.
1.25