The process of Manage Stakeholder Expectations is part of which process?

The process of Manage Stakeholder Expectations is part of which process?

PrepAway - Latest Free Exam Questions & Answers

A.
Executing

B.
Monitoring and Control

C.
Planning

D.
QA

Explanation:
Manage Stakeholder Expectations is part of Monitoring and Control process.