The inputs of the Performance Reporting process include all of the following except for which one?

A.
Performance reviews
B.
Work performance information
C.
Forecasted completion
D.
Performance measurements
Explanation:
Performance reviews are not an input of the Performance Reporting process. The remaining inputs of this process are quality control measurements, project management plan, approved change requests, and deliverables.