Smoothing out resource requirements from period to period is called resource _____.

Smoothing out resource requirements from period to period is called resource _____.

PrepAway - Latest Free Exam Questions & Answers

A.
None of the other alternatives apply.

B.
Leveling.

C.
Quantification

D.
Partitioning

E.
Allocation.