Reserve Analysis a technique not used in:

A.
Estimate Costs
B.
Estimating Activity Duration
C.
Control Costs
D.
Determine Budget
Explanation:
Reserve Analysis: Many cost estimators include reserves, also called contingency allowances, as costs in many schedule activity cost estimates. Reserve Analysis a technique not used in Control Costs.
Absolutely wrong.
7.4 Contol costs tools and Techniques:
.1 Earned value management
.2 Forecasting
.3 To-complete performance index (TCPI)
.4 Performance reviews
.5 Project management software
.6 Reserve analysis
There is no corect answer. All used Reserve Analiysis
0