In which organizational form does the project manager probably have the easiest time in integrating work?

The project manager has, as a prime responsibility, to assure proper integration of activities. In which organizational form does the project manager probably have the easiest time in integrating work?

PrepAway - Latest Free Exam Questions & Answers

A.
Matrix

B.
Pure project

C.
Coordinator

D.
Classical

E.
Expediter