PrepAway - Latest Free Exam Questions & Answers

what is the expected duration in which the activity will be completed?

In the three-point estimating technique, if the most likely estimate for an activity to complete is 100 days, the optimistic estimate is 60 days, and the pessimistic estimate is 200 days, what is the expected duration in which the activity will be completed?

PrepAway - Latest Free Exam Questions & Answers

A.
90 days

B.
100 days

C.
110 days

D.
660 days


Leave a Reply