If project time and cost are not as important as the number of resources used each month, which of the following is the BEST thing to do?

PrepAway - Latest Free Exam Questions & Answers

A.
Perform a Monte Carlo analysis.

B.
Fast track the project.

C.
Perform resource leveling.

D.
Analyze the life cycle costs.