Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible

Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

PrepAway - Latest Free Exam Questions & Answers

A.
Work breakdown structure

B.
Organizational breakdown structure

C.
Resource breakdown structure

D.
Bill of materials