Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT

Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?

PrepAway - Latest Free Exam Questions & Answers

A.
6.1

B.
6.3

C.
6

D.
4