Define Activities is typically performed by which of the following:

A.
Project Manager who created the WBS
B.
Management
C.
Project Team Members responsible for the work package
D.
Project Stakeholder
Explanation:
Define Activities is typically performed by Project Team Members. identify the activities that need to be done to complete the project.