An activity that consumes no time or resources and shows only that a dependency exists between two activities

An activity that consumes no time or resources and shows only that a dependency exists between two activities is called:

PrepAway - Latest Free Exam Questions & Answers

A.
A milestone

B.
A dummy activity

C.
Both 1) A milestone and 2) A dummy activity

D.
A hammock