PrepAway - Latest Free Exam Questions & Answers

All of the following are tools and techniques of the Performance Reporting process except which one?

All of the following are tools and techniques of the Performance Reporting process except which one?

PrepAway - Latest Free Exam Questions & Answers

A.
Performance measurements

B.
Information presentation tools

C.
Time reporting systems

D.
Cost reporting systems

Explanation:
The tools and techniques of the Performance Reporting process are information presentation tools, performance information gathering and compilation, status review meetings, time reporting systems, and cost reporting systems.

One Comment on “All of the following are tools and techniques of the Performance Reporting process except which one?

  1. Ahmet Can Aykut says:

    10.2.2.5 Performance reporting
    Performance reporting is the act of collecting and distributing performance information, including status reports,
    progress measurements, and forecasts. Performance reporting involves the periodic collection and analysis of
    baseline versus actual data to understand and communicate the project progress and performance as well as to
    forecast the project results.
    Performance reporting needs to provide information at an appropriate level for each audience. The format
    may range from a simple status report to more elaborate reports and may be prepared regularly or on an
    exception basis. A simple status report might show performance information, such as percent complete or status
    dashboards for each area (i.e., scope, schedule, cost, and quality). More elaborate reports may include:
    • Analysis of past performance,
    • Analysis of project forecasts (including time and cost),
    • Current status of risks and issues,
    • Work completed during the period,
    • Work to be completed in the next period,
    • Summary of changes approved in the period, and
    • Other relevant information, which is reviewed and discussed.