The performing organization is trying to decide whether to split the contracts department and assign procurement responsibilities to departments directly responsible for the projects. A procurement professional might not want this split to occur because they would lose ___________ in a decentralized contracting environment.

A.
Standardized company project management practices
B.
Loyalty to the project
C.
Experience
D.
Access to others with similar expertise