It would be BEST for the project manager to be in what part of the project management process?

A team member notifies the project manager that the activities comprising a work package are no longer appropriate. It would be BEST for the project manager to be in what part of the project management process?

PrepAway - Latest Free Exam Questions & Answers

A.
Corrective action

B.
Integrated change control

C.
Monitoring and controlling

D.
Project closing