Forecasts, requested changes, recommended corrective actions, and organizational process asset updates are all

Forecasts, requested changes, recommended corrective actions, and organizational process asset updates are all outputs of which process?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk response planning

B.
Risk monitoring and control

C.
Performance reporting

D.
Manage stakeholders