Which of the following is NOT part of stakeholder’s management?

Which of the following is NOT part of stakeholder’s management?

PrepAway - Latest Free Exam Questions & Answers

A.
Identify stakeholder’s need

B.
make sure all the stakeholders are in project plan

C.
Identify stakeholders

D.
make sure all the stakeholders are in communication plan

Explanation:
Stakeholders are NOT in project plan.