Which of the following is NOT part of stakeholder’s management?
A.
Identify stakeholder’s need
B.
make sure all the stakeholders are in project plan
C.
Identify stakeholders
D.
make sure all the stakeholders are in communication plan
Explanation:
Stakeholders are NOT in project plan.