The project manager should:

A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:

PrepAway - Latest Free Exam Questions & Answers

A.
Change the project’s objectives

B.
Call a meeting of the configuration control board

C.
Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

D.
Change the scope baseline

E.
Prepare a variance report