Which of the following must not performed in the project initiation process?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Evaluate historical information
B.
List down business need
C.
List down stakeholders
D.
Create scope statement
Explanation:
Scope statement generally created in planning phase.