Formal written communication is mandated for which of the following?
A.
Both 1) scope changes not part of the original project, and 2) taking exception to a specification.
B.
scope changes not part of the original project
C.
procurement of raw materials
D.
All of the other alternatives apply.
E.
taking exception to a specification