As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the cus

Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.

PrepAway - Latest Free Exam Questions & Answers

A.
Increase, increase.

B.
Increase, decrease.

C.
Remain the same, return to customer.

D.
Decrease, increase.

E.
Decrease, decrease.