You need to report work performance information to management

You are creating a status report to show how your project is progressing. Management is
interested in several key activities and their status. You need to report work performance
information to management. All of the following are example of work performance information you
should include in your report except for which one?

PrepAway - Latest Free Exam Questions & Answers

A.
How the project is performing on its schedule.

B.
Performance of the selected project vendors

C.
Which activities have been started and which activities have been finished.

D.
Percent of completion for the in-progress activities

Explanation:
Vendor performance, while important, is not part of the work performance information.
Management is interested in the how well the project is performing, what activities are currently
underway, and what’s been completed to date.
Answer option A is incorrect the project’s performance on schedule should be reported
Answer option C is incorrect as management is interested in what activities have been started and
finished.
Answer option D is incorrect as management does want to know the percent of completion for the
in-progress activities