which of the following is an output of the Sequence Activities process?

You work as a project manager for BlueWell Inc. According to you, which of the following is an
output of the Sequence Activities process?

PrepAway - Latest Free Exam Questions & Answers

A.
Project scope statement

B.
Project schedule network diagram

C.
Activity list

D.
Organizational process assets

Explanation:
Sequence Activities is one of the twenty processes of the Planning Process group. It is the
process of identifying and documenting relationships among the project activities. Inputs Following
are the inputs to this activity:
Activity list
Activity attributes
Milestone list
Project scope statement
Organizational process assets
Outputs Following are the outputs of the sequence activities process:
Project schedule network diagrams
Project document updates